Power, water supply delay Abuja airport terminal's completion
The Punch The new terminal being constructed at the Nnamdi Azikiwe International Airport, Abuja is 80 per cent complete, the National Assembly, as well as the contractor handling the project announced on Tuesday. However, it was gathered that poor supply of … Abuja Airport International Terminal To Become Operational In February 2018 National Assembly Declares $200m New Abuja Airport 80% Complete Water Supply Delays New Abuja Airport Terminal |